Load Test or Back to Back Test or Sumpner’s Test of Transformer


Load Test of a Transformer is basically carried out for determining the maximum temperature rise of the Transformer. However is not viable to conduct this test by connecting the secondary of the Transformer to rated load. In case of small Transformer, rated load can be connected to the secondary of Transformer but for large Transformer, rated load capable of consuming rated power is not easily available and also this will lead to wastage of energy. Therefore the best and smart way to load a Transformer is to conduct Back to Back Test or Sumpner’s Test. It shall be noted here that, Back to Back Test or Sumpner’s test can also be conducted for calculating the efficiency of a Transformer but it is better to calculate the efficiency of Transformer using Open Circuit Test and Short Circuit Test of Transformer as this will give more accurate result. In this post we will focus on Back to Back Test or Sumpner’s Test of single phase Transformer.

The Back to back Test on single phase transformer requires two identical Transformers.  In this Test, the primaries of two Transformers are connected in parallel and are energized at rated voltage and frequency as shown in figure below.



With Secondary open, the wattmeter W1 records the total core loss occurring in both the Transformers. Now, secondary of both the Transformers are connected in series with their polarity in phase opposition so that the voltage across the terminals ab is zero as indicated by the voltmeter V2. Here it shall be noted that, the basis for selection of range of voltmeter V2 shall be the double of rated secondary voltage of the Transformers. In case, the reading of voltmeter V2 is not zero, this means that the series connection of secondary of Transformer are not in phase opposition and therefore we need to change the connection by just connecting the terminals ad together and check that voltage across bc is zero as indicated by voltmeter V2.

Now, if we short the secondary of Transformers, no current will flow as Vab = 0 and therefore the reading of wattmeter W1 will not change. Now we will inject voltage in the secondary circuit by means of voltage regulator, fed from the source connected to the primary or from a separate source.  The injected voltage is regulated till rated current flow in the secondary circuit. By Transformer Action, rated current now will start flowing in primary circuit too. Note here that, the full load or rated current in primary completes its path as shown by the dotted line in figure above. As this full load current in the primary is not flowing through the current coil of the wattmeter, therefore the reading of wattmeter W1will remain unaltered.

The reading of voltmeter V2will now show the voltage drop due to leakage impedance of both the Transformers. As full load current is flowing in the secondary circuit, the wattmeter W2 will read the total full load ohmic loss of Transformers.
Let us suppose that,


then,

Reading of wattmeter W1=2Pc
Reading of wattmeter W2= 2Poh

Therefore, from the above two reading efficiency of each Transformer can be determined.


From the above discussion, it is quite clear that, even though Transformer is not connected to any load in Sumpner’s Test, rated current is flowing in the primary as well as in the secondary of Transformers and hence full load ohmic and core loss is taking place. If temperature rise of the two Transformers is to be measured, then two Transformers are kept under rated loss condition for several hours till maximum stable temperature is reached.

Comments

Popular posts from this blog

Concept of Subtransient, Transient & Steady State

Open Circuit and Short Circuit Characteristics of Synchronous Machine

Restricted Earth Fault Protection of Transformer